CONSTRUCTION PROJECT UPDATE 10-27-22:

*    Temporary road closures can be expected during paving operations.

STREET FROM TO 2 WEEK OUTLOOK
*Lenape Trail Mohawk Dr Mohawk Dr Water Main connections and removal of old fire hydrants has been completed.

 

Replacement of select driveway aprons and installation of ADA Ramps is complete.

 

Asphalt paving scheduled to begin on Monday October 31st with an anticipated completion date of Friday November 4th.

 

Installation of new force main will be complete by Friday October 28th.

 

Backfilling, topsoiling, and seeding work to be completed by November 4th.

Mohawk Drive Lenape Trail Woodbury-Glassboro Rd Paving scheduled to begin Wednesday November 2nd
East Poplar Street Clinton Avenue Princeton Avenue Final cleanup and punchlist remain.
Monroe Avenue Poplar Mantua Final cleanup and punchlist remain.

 

Two (2) asphalt repairs will have to be completed.

 

The Contractor will be delivering notices to each resident in advance of paving.  We ask that you please adhere to the instructions regarding the relocation of your vehicles to avoid conflict with the roadway paving work. 

In addition, we ask that you refrain from driving on the newly paved roadways until the Contractor removes all barricades and opens the roadways to vehicular traffic.

 

The Contractor will attempt to limit your inconvenience to the greatest extent possible and we ask that you be mindful of the proposed construction and safety of the construction workers.