The Borough awarded a construction contract entitled the 2023 Borough of Wenonah Infrastructure Improvement Project to Earle Asphalt Company.  Listed below is the construction project update for August 8, 2023:

STREET FROM TO 4 WEEK OUTLOOK
N. Clinton Ave Poplar Maple Water main construction and replacement of existing water services is complete.

Utility trenches from Poplar Street to Elm Street scheduled to be paved within next two weeks.

N. Clinton Ave Elm Maple Replacement of existing curbs and driveway aprons and construction of ADA ramps is underway.  Anticipated completion is August 15th.

** Roadway reconstruction scheduled to begin August 10th and completed by August 18th.

N. Clinton Ave will be closed to vehicular traffic and a detour will be in place for duration of paving operations.  Seek alternate routes.

N. Jefferson  Ave    Mantua  Ave Buttonwood All utility improvements are complete.

* Replacement of existing curbs and driveway aprons and construction of ADA ramps is scheduled to begin approximately August 15th.

Maple Street Princeton Synnott Replacement of existing storm sewers at Synnott Avenue is complete.

** Milling & paving scheduled for second week of September.

 

* We remind you that if you reside on a roadway that is scheduled for curb replacement, you are advised that proposed construction will entail disturbance to the Borough’s Right of Way, which is typically sixteen (16) feet perpendicular to the curbline. Should any privately owned improvements be located within the Borough’s Right of Way, i.e. sprinkler systems and/or landscaping improvements, etc. these items will be removed by the Contractor if found to be in conflict with the proposed construction and the responsibility for their repair and/or replacement shall lie solely upon the property owner and NOT the Contractor.

The Contractor will be delivering notices to each resident in advance of concrete curb and driveway replacement in N. Jefferson Avenue. We ask that you please adhere to the instructions regarding the relocation of your vehicles to avoid interference with the Contractor’s work.

** Road closures/detours can be expected during paving operations.  Therefore, we ask that you pay close attention to the posted construction signage and be prepared to use alternate routes to avoid conflict with construction activities. 

          The Contractor will be delivering notices to each resident in advance of paving operations.  We ask that you please adhere to the instructions                           regarding the relocation of your vehicle to avoid interference with the Contractor’s work. 

The Contractor will attempt to limit your inconvenience to the greatest extent possible and we ask that you be mindful of the proposed construction and safety of the construction workers.