The Borough awarded a construction contract entitled the 2023 Borough of Wenonah Infrastructure Improvement Project to Earle Asphalt Company.  Listed below is the construction project update for September 29, 2023:

STREET FROM TO  1 WEEK OUTLOOK
N. Clinton Ave Poplar Maple The contractor will be hydro-seeding the bare soil areas disturbed by the construction and addressing punchlist items, including final clean-up.
N Jefferson Ave Mantua Ave Buttonwood The contractor will be addressing punchlist items, including final clean-up.
*Maple Street Princeton Synnott Roadway milling and paving operations are scheduled for Thursday, October 5th and are expected to be completed by end of day. 

Maple Street, from Marion Avenue to Woodbury-Glassboro Road will be closed to vehicular traffic for duration of paving operations.

Adhere to detour signage and/or seek alternate routes. 

 

 

* Road closures/detours  will be implemented during paving operations.  Therefore, we ask that you pay close attention to the posted construction signage and be prepared to use alternate routes to avoid conflict with construction activities. 

          *The contractor will be delivering notices to each affected resident in advance of paving operations.  We ask that you please adhere to the instructions regarding the relocation of your vehicle to avoid interference with the contractor’s work. 

The contractor will attempt to limit your inconvenience to the greatest extent possible and we ask that you be mindful of the proposed construction and safety of the construction workers.